Turnkey expansion of the 20/110 kV Substation Voštane – electrical part, enabling the connection of the Tijarica and Tarabnik Solar Power Plants with a total connection capacity of up to 63 MVA, for clients Vrtača d.o.o. and Encro – Voštane d.o.o.

Equipement Delivered

  • 110 kV transformer bay
  • Expansion of the grounding system, lightning protection, and outdoor lighting
  • 20 kV switchgear, 20 kV connection for the 63 MVA 110/20 kV transformer, and 20 kV neutral earthing resistor
  • Auxiliary AC power supply system (400/231 V, 50 Hz) with an auxiliary diesel generator and auxiliary DC power supply system (220 V DC) for the Solar Plant Operator's needs
  • Relay protection and automatic voltage regulation (AVR) system for the 110/20 kV transformer, relay protection for the 20 kV resistor and 20 kV switchgear
  • Control, signaling, billing, and operational measurement systems
  • Fire alarm system
  • Station computer under the jurisdiction of the Solar Plant Operator and integration into the remote control system (CDU) of the Solar Plant Operator
  • 110 kV transformer bay relay protection system and expansion of busbar protection and breaker failure protection under HOPS jurisdiction

Scope of Work

  • Preparation of the complete detailed electrical design (execution project)
  • Preparation of relay protection settings
  • Facility construction – electrical part on a turnkey basis
  • Parameterization, configuration, testing, and commissioning of all delivered equipmentParameterization, configuration, testing, and commissioning of all delivered equipment
  • Integration of the bay into the station computer under HOPS (Croatian Transmission System Operator) jurisdiction and into the remote control system (CDU/NDC HOPS)